You have just been appointed Financial Controller of Y, a marketing consultancy.
You are in a meeting with the Chief Executive Officer (CEO) of Y, and have been discussing the need for a major upgrade of all the information systems throughout Y, as they are all very old.
Knowing that major change should be managed effectively, you have suggested that Y should have a ‘systems steering committee’.
Advise the CEO which of the following should be included in the terms of reference of the steering committee.
A . Plan for new systems
B . Develop new systems
C . Manage the project
D . Consider the competitive issues raised by the new system
E . Ensure the new system will meet the company’s goals
Answer: A,D,E