You are the Scrum Master of a project to construct an IT Tech Park. This project requires adhering to stringent quality standards at every stage of development. A Scrum Core Team is formed for this project in which the Scrum Master is supposed to facilitate a “team first” mentality when it comes to quality. You must ensure all of the following to maintain quality in Scrum, EXCEPT:


You are the Scrum Master of a project to construct an IT Tech Park. This project requires adhering to stringent quality standards at every stage of development. A Scrum Core Team is formed for this project in which the Scrum Master is supposed to facilitate a “team first” mentality when it comes to quality. You must ensure all of the following to maintain quality in Scrum, EXCEPT:
A . Any quality related error must be fixed only at the end to ensure that the deliverable is Done.
B . Iterative Product development, repetitive testing, and documentation help ensure quality is inherent in each Done deliverable.
C . Any quality requirement must consider the capacity and willingness of the organization to meet the business need.
D . The changing needs of the customers must be incorporated during the increments.

Answer: B