Work performance information and cost forecasts are outputs of which Project Cost Management process?
A . Estimate Costs
B . Plan Cost Management
C . Determine Budget
D . Control Costs
Answer: D
Work performance information and cost forecasts are outputs of which Project Cost Management process?
A . Estimate Costs
B . Plan Cost Management
C . Determine Budget
D . Control Costs
Answer: D