Why may a Business Change Manager be included within a project board structure of one of the programme’s projects?
A . Monitor the project’s finances against the costs of the programme
B . Provide a specific focus on transition and operational stability
C . Provide the procedures to manage project risks
D . Supply the project team with an understanding of the complete programme
Answer: B