Why is the Initiating a Project process used?
A . To decide which project approach is suitable for the project
B . To fully understand how the project objectives will be achieved before committing significant
C . resources
D . To produce the required Work Packages
E . To enable corporate or programme management to give authorization to deliver a project
Answer: B