There is a database feature requiring three members of a seven person team. A meeting is scheduled at the beginning of the sprint to go over technical needs to complete the story.
Who should the Scrum Master invite to the meeting?
A . The core team and the customer
B . The product owner and key stakeholders
C . The customer and the sponsor
D . The core team and the product owner
Answer: D