Who should manage the tasks of Development Team during the Sprint?

Who should manage the tasks of Development Team during the Sprint?
A . The Project Manager.
B . The Product Owner.
C . The Scrum Master.
D . The Development Team.
E . All of the above.

Answer: D

Explanation:

The Development Team is responsible for managing and tracking the progress of their work during a Sprint