Who must ensure that the work done for a Product Backlog item conforms to the Definition of “Done?”
A . The test team.
B . The Scrum Team.
C . The Scrum Master.
D . The Product Owner.
E . The Development Team.
Answer: E
Explanation:
The Development Team owns the Definition of “Done” and is accountable for the quality of the Product Backlog items.