Who is ultimately responsible for providing requirement specifications to the software- development team?

Posted by: Pdfprep Category: CISA Tags: , ,

Who is ultimately responsible for providing requirement specifications to the software- development team?
A . The project sponsor
B . The project members
C . The project leader
D . The project steering committee

Answer: A

Explanation:

The project sponsor is ultimately responsible for providing requirement specifications to the software-development team.