Who is responsible for engaging the stakeholders?
A . The Business Analyst.
B . The Development Team.
C . The Team Manager.
D . The Project Manager.
E . The Product Owner.
Answer: E
Who is responsible for engaging the stakeholders?
A . The Business Analyst.
B . The Development Team.
C . The Team Manager.
D . The Project Manager.
E . The Product Owner.
Answer: E