While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?
A . Length of Sprint, Agreed Actionable Improvements, Done Criteria, Team Calendar.
B . Assigned Action Items, Business Improvements, Dependencies, Team Calendar.
C . Length of Sprint, Previous Sprint Velocity, Dependencies, Team Calendar.
D . Proof of Concept, Previous Sprint Velocity, Done Criteria, Team Calendar.
Answer: C