Which would be an expected outcome for a new VM deployed into the vSAN cluster?

Posted by: Pdfprep Category: 5V0-21.20 Tags: , ,

The clomd service has stopped on 1 host in a 3 node vSAN cluster. All other services on the host, as well as the other 2, are healthy. Additionally, the unmodified vSAN Default Storage Policy is in use.

Which would be an expected outcome for a new VM deployed into the vSAN cluster?
A . VM deployment will fail.
B . VM deployment will complete but VM 10 will fail.
C . VM deployment will complete but performance will be degraded.
D . VM deployment will be deferred by vCenter.

Answer: C