A project manager is experiencing a project with a high degree of change.
Which type of stakeholder engagement does this project require?
A . Discussing with management
B . Escalating to the sponsors
C . Engaging regularly with stakeholders
D . Engaging only with decision makers
Answer: C
Explanation:
Reference: https://opentextbc.ca/projectmanagement/chapter/chapter-5-project-stakeholders-projectmanagement/