Posted by: Pdfprep
Post Date: April 13, 2021
Many companies use Critical Path Analysis (CPA) to manage projects.
Which TWO of the options below could be identified from a CPA diagram?
A . The activities which need to be completed before the next activity can start.
B . The resource usage variance for each activity.
C . The activities which can’t overrun without delaying the whole project.
D . The probable time for each activity.
Answer: A,C
Leave a Reply