Which TWO of the options below could be identified from a CPA diagram?


Many companies use Critical Path Analysis (CPA) to manage projects.

Which TWO of the options below could be identified from a CPA diagram?
A . The activities which need to be completed before the next activity can start.
B . The resource usage variance for each activity.
C . The activities which can’t overrun without delaying the whole project.
D . The probable time for each activity.

Answer: A,C

Leave a Reply

Your email address will not be published.