Which two of the following measures would give the best indication of likely product quality?
a) Number of hours of overtime worked.
b) Number of test runs.
c) Coverage of requirements achieved.
d) Defect trends.
e) Budget sent so far.
A . a and c.
B . b and d.
C . c and d.
D . d and e.
Answer: C