Which tool should the Scrum Master use to provide these updates?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities.

Which tool should the Scrum Master use to provide these updates?
A . Shared vision statement and sprint goal
B . Release burnup chart
C . Velocity metrics
D . Iteration burndown chart

Answer: D

Explanation:

Reference: https://www.projectmanager.com/blog/burndown-chart-what-is-it