Which tool should a project manager consider to deal with multiple sources of risk?

Which tool should a project manager consider to deal with multiple sources of risk?
A . An updated risk register
B . Risk breakdown structure
C . Issue log
D . Stakeholder register

Answer: B

Explanation:

Reference: https://www.pmi.org/learning/library/risk-breakdown-structure-understand-risks-1042