Which three actions should you perform in sequence?

Posted by: Pdfprep Category: MB-320 Tags: , ,

DRAG DROP

A company uses Dynamics 365 Process manufacturing.

Employees work a half day so that they can attend a company event. You have a rush order that must be completed that same day.

After reviewing the net requirements of the batch order, only 400 of the total quantity of 1400 units must be completed today. The production manager must retain the original batch number as the quantity of 400. The original batch number must appear on documentation for the customer.

You need to split the batch order onto two orders.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Answer: