Which theme is being applied?


MANAGING PRODUCT DELIVERY

The team manager for the production of the ‘marketing materials’ has identified that they will not be ready within the timescale agreed in the work package. The team manager has sufficient tolerance to take corrective action. As a result, additional resources have been assigned to this work package .

Which theme is being applied?
A . Risk
B . Organization
C . Progress
D . Change

Answer: A

Leave a Reply

Your email address will not be published.