Which test management control option is most appropriate to adopt under these circumstances? 2 credits
A . Introduce mandatory evening and weekend working to retrieve the 3 week slippage.
B . Reconsider the exit criteria and review the test plan in the context of the current situation.
C . Advise the user community regarding the reduced scope of requirements and the additional incremental delivery.
D . Arrange a meeting with the user community representatives to discuss the user interface.
Answer: B