Which technique is used by a project team to estimate the amount of work that can be done per iteration?
A . Velocity measurement
B . Relative prioritization
C . Planning Poker
D . Release planning
Answer: A
Which technique is used by a project team to estimate the amount of work that can be done per iteration?
A . Velocity measurement
B . Relative prioritization
C . Planning Poker
D . Release planning
Answer: A