Which tasks should a project manager perform in order to manage the project schedule effectively?
A . Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Develop Schedule
B . Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule
C . Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities, Develop Schedule
D . Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Estimate Cost of Activities, Develop Schedule
Answer: B
Explanation: