An administrator would like to add a new server into an existing vSphere cluster. The servers are running Intel processors. The administrator needs to ensure that the new server can be added to the cluster with the same processor baseline as the existing servers.
Which strategy should be used to achieve this goal?
A . Fault Tolerance
B . Enhanced vMotion Compatibility
C . vSphere vMotion
D . vSphere High Availability
Answer: B