PdfPrep.com

Which stories should the team include in Sprint 1, without splitting the stories?

An Agile team expects a velocity of 8.

During sprint planning, the stories were estimated and prioritized in the following order:

Story A_4Story Points

Story B_2Story Points

Story C_3 Story Points

Story D_2Story Points

Which stories should the team include in Sprint 1, without splitting the stories?
A . Stories A, C, and D
B . Stories A, B, and C
C . Stories A, B, and D
D . Stories B, C, and D

Answer: C

Exit mobile version