Which statement is FALSE?
A . A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
B . A project’s output is any of the project’s specialist products
C . A project benefit is only realized after the project has closed
D . A project outcome is the result of the change derived from using the project’s outputs
Answer: C