Which statement correctly describes the differences between Project Assurance and quality assurance?
A . Project Assurance provides assurance to the project’s stakeholders whereas quality assurance provides assurance to the wider corporate or programme organization
B . They are both the responsibility of the Project Board, but Project Assurance may be delegated
C . Quality assurance is internal to the project, whereas Project Assurance is independent of the project
D . Project Assurance must be independent of the Project Manager, whereas quality assurance is the responsibility of the Project Manager
Answer: A