Which statement best describes the responsibilities of a risk actionee?
A . Identifying risks to the project that might occur in their department
B . Owning and authorizing the use of the risk budget to fund risk responses
C . Managing, monitoring and controlling of all aspects of an assigned risk
D . Carrying out a risk response action to respond to a particular risk
Answer: C