Which statement accurately depicts what changes can be made to requirements after they are baselined?
A . Requirements cannot be changed once user acceptance testing begins.
B . Requirements can be changed through a defined process.
C . Requirements can be changed only with sponsor approval.
D . Requirements cannot be changed once development begins.
Answer: B