Which statement about the Directing a Project process is FALSE?
A . Supports the PRINCE2 principle of manage by exception
B . Is triggered by a request to initiate a project
C . Covers the day-to-day activities of the Project Manager
D . Provides a mechanism for the Project Board to assure that there is continued business justification
Answer: C