A construction company that is one of ABC Company’s key clients has agreed to provide a member of the staff to review and comment on the ‘e-learning course’.
Which stakeholder interest should the member of staff represent, and why?
A . Supplier, because this stakeholder provides the expertise required by the project.
B . Supplier, because this stakeholder is an external supplier.
C . User, because this stakeholder may train its staff using the ‘e-learning course’.
D . User, because this stakeholder ensures that the project provides value for money.
Answer: C