Posted by: Pdfprep Category: CAPM Tags: CAPM exam questions, CAPM practice exam, CAPM Certification Post Date: December 8, 2020 Pdfprep2020-12-08T14:28:20+00:00 Which stakeholder approves a project’s result?A . CustomerB . SponsorC . SellerD . Functional manager View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.