The project management plan requires the acquisition of a special part available from a supplier located abroad.
Which source selection method is being used?
A . Least cost
B . Qualifications only
C . Sole source
D . Fixed budget
Answer: C
The project management plan requires the acquisition of a special part available from a supplier located abroad.
Which source selection method is being used?
A . Least cost
B . Qualifications only
C . Sole source
D . Fixed budget