Which set of tools and techniques is useful for estimating activity durations for the project schedule?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which set of tools and techniques is useful for estimating activity durations for the project schedule?
A . Brainstorming, Monte Carlo Simulation, analogous estimation
B . Three-point estimation, resources leveling, iteration burndown chart
C . Milestone charts, parametric estimation, schedule baseline
D . Parametric estimation, three-point estimation, analogous estimation

Answer: D

Explanation: