Which role is responsible for determining when it is most appropriate to update the Sprint Backlog?

Posted by: Pdfprep Category: PSM II Tags: , ,

Which role is responsible for determining when it is most appropriate to update the Sprint Backlog?
A . The Product Owner
B . The Development Team
C . The Scrum Team
D . The Scrum Master

Answer: B

Explanation:

The Development Team is responsible for tracking the remaining work of the Sprint.