Posted by: Pdfprep
Post Date: October 25, 2020
Which role is responsible for determining when it is most appropriate to update the Sprint Backlog?
A . The Product Owner
B . The Development Team
C . The Scrum Team
D . The Scrum Master
Answer: B
Explanation:
The Development Team is responsible for tracking the remaining work of the Sprint.
Leave a Reply