Which role does PRINCE2 state would contribute expertise in specialist tools and techniques such as planning and control tools and risk analysis?
A . Team Manager
B . Senior Supplier
C . Project Support
D . Project Assurance
Answer: C
Which role does PRINCE2 state would contribute expertise in specialist tools and techniques such as planning and control tools and risk analysis?
A . Team Manager
B . Senior Supplier
C . Project Support
D . Project Assurance
Answer: C