A business analyst (BA) is planning the requirements attributes. The BA received a long list of requirements that must be implemented in different phases.
Which requirements attribute can the BA include to allocate the requirements to the proper phase?
A . Status
B . Author
C . Priority
D . Source
Answer: C
Explanation:
Priority: indicates relative importance of requirements. Priority can refer to the relative value of a requirement or to the sequence in which it will be implemented.