Posted by: Pdfprep Category: PRF Tags: PRF exam questions, PRF practice exam, PRINCE2 Foundation Post Date: December 1, 2020 Pdfprep2020-12-01T05:38:07+00:00 Which regular report provides the Project Board with a summary of stage status?A . Communication Management StrategyB . Project BriefC . Highlight ReportD . Checkpoint Report View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.