Scrum Masters must be able to manage sprints in a particular project, but they are unable to do so. You need to recommend an action to the Jira administrator which satisfies their requirement.
Which recommendation will definitely NOT satisfy their requirement?
A . Add Application access (Jira Core) to the Manage Sprints permission.
B . Add the Scrum-Masters project role to the Manage Sprints permission.
C . Add individual users to the Scrum-Masters project role.
D . Add the Scrum-Masters group to the Manage Sprints permission.
Answer: C