Which Project Time Management process includes bottom-up estimating as a tool or technique?

Which Project Time Management process includes bottom-up estimating as a tool or technique?
A .  Estimate Activity Resources
B .  Sequence Activities
C .  Estimate Activity Durations
D .  Develop Schedule

Answer: A