Which project document is updated in the Control Stakeholder Engagement process?
A . Project reports
B . Issue log
C . Lessons learned documentation
D . Work performance information
Answer: B
Which project document is updated in the Control Stakeholder Engagement process?
A . Project reports
B . Issue log
C . Lessons learned documentation
D . Work performance information
Answer: B