Which project controls should be established for the Outsourcing project?


Which project controls should be established for the Outsourcing project?
A . Highlight Reports to the Project Manager; Exception Reports to the Project Board when project tolerances are forecast to be exceeded.
B . Highlight Reports to the Project Board; Exception Reports to corporate management when stage
tolerances are forecast to be exceeded.
C . Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or project tolerances are forecast to be exceeded.

Answer: C