Posted by: Pdfprep
Post Date: October 29, 2020
Which product would contain information on project and stage tolerance status, products completed during the period and a summary of actual or potential problems and risks?
A . Product Status Account
B . Communication Management Strategy
C . Highlight Report
D . Risk Register
Answer: C