Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?
A . Checkpoint Report
B . End Stage Report
C . End Project Report
D . Product Status Account
Answer: B
Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?
A . Checkpoint Report
B . End Stage Report
C . End Project Report
D . Product Status Account
Answer: B