Which product should show that the staff photo sessions were disruptive to the Engineering Department as they had been scheduled during peak work times without consultation with the Engineering Manager?
A . Follow-on action recommendations
B . Lessons Report
C . Project closure notification
D . Risk Register
Answer: B