Which product produced by the Project Manager would contain information on ‘products completed in the period’?
A . Product Status Account
B . Checkpoint Report
C . Highlight Report
D . Exception Report
Answer: C
Which product produced by the Project Manager would contain information on ‘products completed in the period’?
A . Product Status Account
B . Checkpoint Report
C . Highlight Report
D . Exception Report
Answer: C