Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
A .  Controlling a Stage
B .  Closing a Project
C .  Directing a Project
D .  Managing a Stage Boundary

Answer: D