Which process numerically analyzes the effect of identified risks on overall project objectives?
A . Plan Risk Management
B . Plan Risk Responses
C . Perform Quantitative Risk Analysis
D . Perform Qualitative Risk Analysis
Answer: C
Explanation:
Process: 11.4 Perform Quantitative Risk Analysis
Definition: The process of numerically analyzing the effect of identified risks on overall project objectives.
Key Benefit: The key benefit of this process is that it produces quantitative risk information to support decision making in order to reduce project uncertainty.
Inputs