The project manager is working in the processes of Project Resource Management.
Which process is the project manager developing if they are using parametric estimation?
A . Plan Resource Management
B . Estimate Activity Resources
C . Estimate Costs
D . Acquire Resources
Answer: A
Explanation:
Reference: https://opentextbc.ca/projectmanagement/chapter/chapter-11-resource-planning-projectmanagement/