Which process is the project manager developing if they are using parametric estimation?

Posted by: Pdfprep Category: CAPM Tags: , ,

The project manager is working in the processes of Project Resource Management.

Which process is the project manager developing if they are using parametric estimation?
A . Plan Resource Management
B . Estimate Activity Resources
C . Estimate Costs
D . Acquire Resources

Answer: A

Explanation:

Reference: https://opentextbc.ca/projectmanagement/chapter/chapter-11-resource-planning-project­management/