Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
A . Develop Schedule
B . Create VVBS
C . Estimate Activity Resources
D . Define Scope
Answer: B
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
A . Develop Schedule
B . Create VVBS
C . Estimate Activity Resources
D . Define Scope
Answer: B